Project Manager
Stakeholder
Customer
Executive Sponsor
Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()A、executive IT managerB、projectmangerC、change control boardD、projectsponsor
点击查看答案
()means that every project has a definite beginning and a definite end.A、Project phaseB、UniqueC、TemporaryD、Closure
Who is responsible for authorizing closure of the project?()A、Project ManagerB、StakeholderC、CustomerD、Executive Sponsor
Why does a project manager need an executive sponsor?()A、To keep the project team focused on its workB、To provide behind-the-scenes assistance with organizational commitment and supportC、To sign-off on user requirementsD、To negotiate contracts with outside vendors
单选题Who is responsible for authorizing closure of the project?()A Project ManagerB StakeholderC CustomerD Executive Sponsor
单选题Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.A BenefitcontributionB ExpertjudgmentC ScoringmodelsD Flowcharting
单选题Why does a project manager need an executive sponsor?()A To keep the project team focused on its workB To provide behind-the-scenes assistance with organizational commitment and supportC To sign-off on user requirementsD To negotiate contracts with outside vendors