The most crucial time for project risk assessment is ( ).A、when a problem surfacesB、during the planning phaseC、during the close-out phaseD、after the project schedule has been published

题目内容(请给出正确答案)

The most crucial time for project risk assessment is ( ).

  • A、when a problem surfaces
  • B、during the planning phase
  • C、during the close-out phase
  • D、after the project schedule has been published
参考答案和解析
正确答案:B